The following statements refer to situations occurring in Process Q of an organisation which operates a series of
consecutive processes:
(i) Direct labour is working at below the agreed productivity level.
(ii) A machine breakdown has occurred.
(iii) Direct labour is waiting for work to be completed in a previous process.
Which of these situations could give rise to idle time?
A (i) and (ii) only
B (i) and (iii) only
C (ii) and (iii) only
D (i), (ii) and (iii)
C