| A company uses absorption costing with a predetermined hourly overhead absorption rate. The following situationsarose last month:
 (i) Actual hours worked exceeded planned hours.
 (ii) Actual overhead expenditure exceeded planned expenditure.
 Which of the following statements is correct?
 A Situation (i) would cause overheads to be over absorbed and situation (ii) would cause overheads to be          under absorbed.
 B Situation (i) would cause overheads to be under absorbed and situation (ii) would cause overheads to be over
 absorbed.
 C Both situations would cause overheads to be over absorbed.
 D Both situations would cause overheads to be under absorbed.
 A
 |