每日一练F2 答案回复可见
<p>A company uses absorption costing with a predetermined hourly overhead absorption rate. The following situations<br/>arose last month:<br/>(i) Actual hours worked exceeded planned hours.<br/>(ii) Actual overhead expenditure exceeded planned expenditure.<br/>Which of the following statements is correct?<br/>A Situation (i) would cause overheads to be over absorbed and situation (ii) would cause overheads to be under absorbed.<br/>B Situation (i) would cause overheads to be under absorbed and situation (ii) would cause overheads to be over<br/> absorbed.<br/>C Both situations would cause overheads to be over absorbed.<br/>D Both situations would cause overheads to be under absorbed.</p><p>A<br/></p> d <p>不</p> b C 辛苦了老师!happy new year!X